EPOD systems
Commissioning activities on EPOD-related power infrastructure: installation readiness, field verification, interface checks and test progression.
REFERENCE / DATA CENTER COMMISSIONING
Commissioning engineering experience on mission-critical electrical and mechanical infrastructure within the atNorth FIN04 Myllykoski data center project in Kouvola, Finland.
COMMISSIONING ENGINEERING / FIELD SCOPE
This reference is limited to commissioning engineering performed within the FIN04 project environment. The scope covers field-level electrical and mechanical verification, functional checks, measurements and hardware inspection before systems are released toward integrated operation.
Commissioning activities on EPOD-related power infrastructure: installation readiness, field verification, interface checks and test progression.
Verification of 630 A electrical feeds, associated hardware and field measurements supporting safe energisation and functional testing.
Commissioning and functional verification of chiller-related systems and their electrical/control interfaces as part of cooling-system readiness.
Generator commissioning support, hardware checks and verification of interfaces within the resilient standby-power architecture.
Field measurements on buses and connected hardware, recorded against commissioning requirements and installation status.
Inspection and verification of installed equipment, connections and system interfaces before functional and integrated test stages.
FIN04 / MYLLYKOSKI
Visual context from the Myllykoski data center project. The construction photograph shows the live site environment; the second image is a project visualisation and is labelled separately so that photography and concept material are not mixed.
SITE / CONSTRUCTION PHASE
PROJECT VISUALISATIONSYSTEM VIEW
PUBLIC PROJECT CONTEXT
atNorth currently describes FIN04 as a 45-hectare Myllykoski mega campus in Kouvola with 430 MW power capacity and a path to several hundred additional megawatts. The campus is intended for both colocation and build-to-suit deployments. These figures describe the overall atNorth campus — not Determinova’s commissioning scope.
Scope statement. This case study describes commissioning experience within the Myllykoski FIN04 project environment. It does not state or imply that Determinova Oy designed, supplied, owned, operated or acted as the main contractor for the FIN04 campus. Project-owner and campus-scale information is based on publicly available atNorth material.
DATA CENTER COMMISSIONING